Alcross Day 17

IMG_2416

Crown moulding went up today and so did the hardibacker in the tub surround. The painters get to work on the exterior! What a relief! Final window was installed!

Continue Reading →

Alcross Day 16

IMG_2400

Cabinet Assembly occured today. They are going to look beautiful. All hardwood construction with dovetail box  and soft close hinges. Beautiful cream finish! At the end of the day there were a few parts missing so those will have to be rushed out to complete the job.

Continue Reading →

Alcross Day 15

IMG_2398

Kitchen cabinet Installation begins. Exterior paint continues!

Continue Reading →

Alcross Day 14

IMG_2394

Exterior Painting continues

Continue Reading →

Alcross Day 13

IMG_2420

Windows being installed!

Continue Reading →

Alcross Day 12

IMG_2398

Interior doors hung. Work continuing on exterior. Doorway from bedroom to garage drywall repair Windows delivered Kitchen cabinets delivered.

Continue Reading →